What is a Field Change Directive and when is it used?

Prepare for the Construction Quality Management (CQM) USACE Test with engaging quizzes. Study with comprehensive flashcards and multiple choice questions, each equipped with detailed explanations. Ace your exam with confidence!

Multiple Choice

What is a Field Change Directive and when is it used?

Explanation:
A Field Change Directive is an owner-issued instruction to implement a change in the field before a formal Change Order is issued, used for urgent conditions. It allows work to proceed immediately when waiting for a formal Change Order would jeopardize safety, schedule, or performance. The directive authorizes the change in the field while the cost, time impact, and final contract basis are resolved later, usually through a Change Order or other contract modification. It’s not a safety permit, not a post-construction amendment, and not the standard Change Order, which is the formal contract modification processed through the usual channels. For example, if an unexpected condition is found that needs quick action to keep the project moving or to maintain safety, an FCD can authorize the change right away, with the understanding that the final terms will be set in a later Change Order.

A Field Change Directive is an owner-issued instruction to implement a change in the field before a formal Change Order is issued, used for urgent conditions. It allows work to proceed immediately when waiting for a formal Change Order would jeopardize safety, schedule, or performance. The directive authorizes the change in the field while the cost, time impact, and final contract basis are resolved later, usually through a Change Order or other contract modification. It’s not a safety permit, not a post-construction amendment, and not the standard Change Order, which is the formal contract modification processed through the usual channels. For example, if an unexpected condition is found that needs quick action to keep the project moving or to maintain safety, an FCD can authorize the change right away, with the understanding that the final terms will be set in a later Change Order.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy